The installation of 72 Nordex N149/5.x MW turbines – with a hub height of 105 metres and a rotor diameter of 149 metres – was completed in the 4th quarter 2021. These employ the very latest wind turbine technology and provide renewable energy with no CO2 emissions and the least possible impact on the surrounding natural environment.
Øyfjellet Wind Park will annually produce around 1,3 TWh. This is enough energy for 39% of Alcoa’s annual electricity needs, or for 82,500 households, around 178,200 people. This corresponds to 73% of all those who live in Nordland.
Annual expected production from the wind power plant is based on many years of weather data collection from measurement masts placed in the area designated for wind power. It starts with the maximum expected average production and subtracts losses due to various parameters, including electrical losses, icing, contractual availability, etc. Based on this, an annual expected production emerges, and for wind power, it is common practice to calculate what is referred to as P50, P75, and P90. At ØWAS, the following calculations have been performed:
P50 indicates a production of 1.3 TWh
P70 indicates a production of 1.2 TWh
P90 indicates a production of 1.14 TWh
Aluminium producer Alcoa, which is Mosjøen’s cornerstone industry, has purchased all power production from the wind park for the next 15 years. This guarantees opportunities for growth and contributes to safeguarding hundreds of Norwegian jobs.
The Municipality of Vefsn covers an area of 1,849 km2. The licenced area covers 40 km2, around 2% of the municipality. The roads, turbines and buildings cover 2-3% of the licenced area. The wind park is built on a consetrated area, and adjustments and improvements have continuously been made in line with feedback from the local community.
2023
The project was taken over
Øyfjellet Wind took over the wind park from the developer
2022
All turbines put into operation
All the 72 turbines were put into operation
2021
72 turbines are installed
All 72 turbines are installed
MTA plan approved
The Ministry of Petroleum and Energy approved the environmental, transport and construction plan (MTA) for the development at Øyfjellet.
The municipal council in Vefsn approved agreement
The municipal council in Vefsn unanimously approved the agreement on the wind power plant at Øyfjellet on Thursday, 17 June. For Vefsn municipality, the agreement means that the municipality will receive a total of NOK 422.5 million over the granted concession period of 25 years.
2020
Construction begins
Construction of internal roads, crane pads and turbine foundations.
Construction of transmission line
Construction of 132 kV transmission line between the wind park and Marka substation.
Construction of switchgear
Construction of 132 kV switchgear for connecting the wind park to Marka substation.
Objection review from NVE
NVE decides not to recognise the received objections to the ETC plan for the Øyfjellet wind power installation. NVE states that the assessments conducted have been carried out in compliance with the relevant regulations and the established assessment programme. The case has been submitted to the Ministry of Petroleum and Energy for the final decision.
2019
Detailed plans approved
The detailed plans for realising the wind park – the environment, transport and construction (ETC) plans – are submitted. The plans are designed to ensure the least invasive development possible. Øyfjellet is taken out of the planning area after local consultation. The plans are approved by NVE in December 2019.
Main contractor
Veidekke is selected as the main contractor, alongside a number of local businesses as sub-contractors.
Road construction begins
Construction of the access road and improvements to Tveråveien begin.
Supplier of transmission line
Linka, from the Municipality of Inderøy, is selected to supply the 132 kV transmission line between the wind park and Marka substation.
Supplier of the interface between transmission line and substation
Helgeland Kraft, with headquarters in Mosjøen, is selected to supply the interface between the transmission line and Marka substation. This involves the delivery of 132kV main breaker to Marka substation.
Supplier of operations and maintenance of turbines
Nordex is selected as supplier of operations and maintenance of turbines, and is set to become a long-term member of the local business community.
2018
Long-term power purchasing agreement
In order to secure access to local power, a long-term power purchasing agreement is agreed to the effect that all wind power produced for the next 15 years will go to the Alcoa aluminium works in Mosjøen.
Capacity
NVE grants permission for 400 megawatt capacity.
2016
Final authorization
The Ministry of Petroleum and Energy grants final authorization for the project.
2014
Application submitted
Licence application submitted.
Support from the Municipal Council
Vefsn Municipal Council supports the application. Following dialogue with the local community, it is decided that the Øyfjellet area around Stortuva should not be developed.
License for construction given
The license for the construction of the wind park is given by NVE.
2011
Project agreement
Local landowners and industry agree to the project to provide more green energy to industry.
Privacy Overview
This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.
Strictly Necessary Cookies
Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.
If you disable this cookie, we will not be able to save your preferences. This means that every time you visit this website you will need to enable or disable cookies again.
3rd Party Cookies
This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.
Keeping this cookie enabled helps us to improve our website.
Please enable Strictly Necessary Cookies first so that we can save your preferences!