Will the energy produced at Øyfjellet Wind Park be exported to Europe?

No. Alcoa, which is Mosjøen’s cornerstone industry, is to buy all the power produced for the first 15 years. Helgeland Kraft owns the main grid and is responsible for connecting the power transmission line to Marka substation by means of a 132 kV main breaker inside Marka substation.

The construction contribution covers all expenses involved, therefore ensuring that the development of Øyfjellet Wind Park will not lead to increased grid rental costs for consumers in the area.